Home / Bengaluru / Bengaluru City Railway Station: Escalators Withdrawn Within Hours of Launch
Under Repeat Repair

Bengaluru City Railway Station: Escalators Withdrawn Within Hours of Launch

Blunderlust rating★★★★★ 4.3 / 5 · 136 reviews⌖ Bengaluru City (KSR Bengaluru) Railway Station, Platforms 1 and 5, BengaluruEntry #20 in Bengaluru

On record

Four escalators sanctioned in the 2009 Railway Budget at a cost of ₹3 crore were commissioned with fanfare at Bengaluru City railway station, but two of them were pulled out of service within hours after two elderly passengers fell while using them. Only three of the four planned escalators had even been installed at launch, with the fourth delayed to the following month.

The official record states: "Railway officials said "the situation changed suddenly after two passengers fell down. The service was withdrawn considering safety," attributing the falls to passenger unfamiliarity rather than any acknowledged design or installation defect."

“Three crore of escalators, two of them switched off the day they were switched on.”— Blunderlust Editorial Desk

Sources

  • https://www.deccanherald.com/amp/story/india%2Fkarnataka%2Fbengaluru%2Fescalators-stopped-hours-launch-rly-2175423

Visitor reviews Satire

“Two of the four escalators were switched off the same day they were switched on, after two elderly passengers fell.”
RK R. Kumar · Bengaluru★★★★★
“Three crore for four escalators, of which three were installed and two immediately withdrawn. The maths is the story.”
SP S. Patel · Bengaluru★★★★★
“Officials put the falls down to passenger unfamiliarity, so the passengers were the defect.”
AF A. Fernandes · Bengaluru★★★★★
Blunderlust RecordBL/BEN/2010/RAI
Status
Under repeat repair / withdrawn from service
Category
Railway Station
State
Karnataka
Year
2010
Cost to taxpayers
₹3 Cr

Your passport

Unstamped

Stay a moment and this entry goes in your passport.

Bengaluru
0 of 24
Nationwide
0
Rank
None yet

1 more for Tourist.

View your passport →

Nearby Attractions

While you're in the area

Full Bengaluru guide →
Under Repeat Repair
Citywide (142 public toilets audited) · Public toilet

Bengaluru Public Toilets

A 2026 citizen-led audit of 142 public toilets across Bengaluru found 26% non-functional, only 6 rated "very clean," and 58% with persistent foul odour, despite the city having roughly just one public toilet for every 30,000 residents. The findings renewed calls for urgent sanitation infrastructure and management reforms.

Blunderlust rating ★ 3.5 · 282 reviewsOn record 2026
Under Repeat Repair
Kadabagere, Major Arterial Road (MAR), West Bengaluru · Road

Major Arterial Road, Kadabagere

A newly built ₹500-crore stretch of Bengaluru's Major Arterial Road near Kadabagere developed multiple large sinkholes across a 20-metre stretch just days before its scheduled inauguration on June 27, 2026. A viral video showed gaping craters on the still-uninaugurated road, which remained under contractor control and had not yet been formally handed over to the BDA.

Blunderlust rating ★ 4.1 · 722 reviewsOn record 2026
Under scrutiny / Ongoing financial stress
Citywide: Namma Metro Phase 1 & Phase 2 (BMRCL) · Metro station

Namma Metro Land-Cost Overrun

A CAG report tabled in August 2026 found that "improper estimation of land requirements," combined with prolonged delays in land acquisition, inflated Namma Metro's Phase 1 and 2 costs by over ₹6,600 crore. It also found BMRCL posted continuous cash losses from 2013-14 to 2021-22 and remains dependent on state government support to service its debt, with actual ridership falling well short of projections used to justify the heavy-metro design.

Blunderlust rating ★ 3.8 · 168 reviewsOn record 2026

Spread the word

Share this one.

Download the card for Bengaluru City Railway Station: Escalators Withdrawn Within Hours of Launch and send it to a friend.

Submit a Blunder →
Blunderlust

The civic travel guide to the India we were promised in the brochure. Reviewed without fear, favour, or functioning streetlights.

Destinations

  • Mumbai
  • Bengaluru
  • Ahmedabad
  • All cities

Categories

  • All wonders
  • Flyovers to nowhere
  • Bridges on notice
  • Roads reimagined
  • Skywalks to nowhere
  • Metro in progress
  • Public toilets, theoretically
  • Airports awaiting flights
  • Stations under redevelopment
  • Bus stands nobody uses

The Guide

  • Destinations
  • Submit a blunder
  • The Ledger
  • Photo credits
  • Contact desk

“Bureaucracy is a construction by which a person is conveniently separated from the consequences of his or her actions.”

— Nassim Nicholas Taleb, Skin in the Game
NOTICE — Entries document real, publicly reported infrastructure projects, sourced from news reports and RTI replies (see each entry for citations). Star ratings, reviews and editorial tone are satirical framing; the underlying facts are not, and are omitted for entries involving loss of life. Not affiliated with any government body, political party, or foreign agency.© 2026 Blunderlust · File No. BL/2026/POTHOLE/01
Spread the word

Join the mission.

This is a public list of failed government projects, kept so they stay on record. Pick either one — both take a minute.

1

Share this with at least one person

Just one is enough. Copy the link and send it to friends & family who would find this useful.

2

Know a failed project near you? Tell us

Know a project that failed or never opened? Fill a short form; we just need a news link as proof.

Submit a blunder →
thank you, genuinely!
Blunderlust