On record
The Walled City extension (Phase 1B) opened years late in September 2020. Its further extension (Phase 1C) began underground construction only in 2024 and remains unfinished. Phase 2, first proposed for 2021 completion, only got its first civil contract awarded in January 2026, pushing real completion to around 2028-2031.
The official record states: "Not specified: no single official explanation; delays stemmed from repeated DPR revisions, tendering, and a consultancy JV legal dispute on Phase 2."
“Phase 1B late, Phase 1C unfinished, Phase 2 awarded five years after it was due to open.”— Blunderlust Editorial Desk
Sources
- https://en.wikipedia.org/wiki/Jaipur_Metro
- https://themetrorailguy.com/2026/01/18/ceigall-sam-jv-wins-jaipur-metro-phase-2s-first-civil-contract-2c-01/
Visitor reviews Satire
“Rode to Badi Chaupar under the Walled City, which opened years late and remains the most finished part of the plan.”
“Phase 1C has been under the old city since 2024, and the shopkeepers above it have stopped asking when.”
“Phase 2 was meant to be running by 2021 and got its first civil contract in 2026. Twelve thousand crore, starting now.”