Under Construction

Jaipur Metro

Blunderlust rating★★★★★ 4.3 / 5 · 808 reviews⌖ Chandpole–Badi Chaupar corridor (Phase 1B/1C); Ambabari–Sitapura corridor (Phase 2, Orange Line), JaipurEntry #02 in Jaipur

On record

The Walled City extension (Phase 1B) opened years late in September 2020. Its further extension (Phase 1C) began underground construction only in 2024 and remains unfinished. Phase 2, first proposed for 2021 completion, only got its first civil contract awarded in January 2026, pushing real completion to around 2028-2031.

The official record states: "Not specified: no single official explanation; delays stemmed from repeated DPR revisions, tendering, and a consultancy JV legal dispute on Phase 2."

“Phase 1B late, Phase 1C unfinished, Phase 2 awarded five years after it was due to open.”— Blunderlust Editorial Desk

Sources

  • https://en.wikipedia.org/wiki/Jaipur_Metro
  • https://themetrorailguy.com/2026/01/18/ceigall-sam-jv-wins-jaipur-metro-phase-2s-first-civil-contract-2c-01/

Visitor reviews Satire

“Rode to Badi Chaupar under the Walled City, which opened years late and remains the most finished part of the plan.”
QS Q. Sheikh · Jaipur★★★★★
“Phase 1C has been under the old city since 2024, and the shopkeepers above it have stopped asking when.”
EK E. Kohli · Jaipur★★★★★
“Phase 2 was meant to be running by 2021 and got its first civil contract in 2026. Twelve thousand crore, starting now.”
CR C. Raman · Jaipur★★★★★
Blunderlust RecordBL/JAI/2020/MET
Status
Under construction / repeatedly delayed for over a decade
Category
Metro station
State
Rajasthan
Year
Phase 1B opened Sept 2020; Phase 1C started 2024 (incomplete); Phase 2 first contract awarded Jan 2026
Cost to taxpayers
₹856 CrPhase 1C ~₹856 crore; Phase 2 (42.8km) ~₹12,260 crore

Your passport

Unstamped

Stay a moment and this entry goes in your passport.

Jaipur
0 of 10
Nationwide
0
Rank
None yet

1 more for Tourist.

View your passport →

Nearby Attractions

While you're in the area

Full Jaipur guide →
Under Repeat Repair
Dravyavati River corridor through Jaipur, including Ambawadi and the stretch from Shastri Nagar to Vidyadhar Nagar · Other

Dravyavati River Rejuvenation Project: Missed Deadlines and Court Contempt

A flagship ₹1,676-crore project to rejuvenate Jaipur's Dravyavati river (formerly the sewage-choked Amanishah Nallah) missed its October 2018 completion deadline, left tributaries like Kartarpura Nulla untouched (causing dangerous sinkholes during rain, now under High Court litigation), and continues receiving untreated sewage from the Walled City, Sanganer and Pratap Nagar. In 2026 the Rajasthan High Court found the JDA had ignored a NEERI report's recommendations for constructing cement concrete drain channels along the river and demanded an explanation for the continued delay.

Blunderlust rating ★ 4.6 · 994 reviewsOn record 2026
Under Repeat Repair
Tonk Road (near JMC headquarters), plus Sodala Road, Meera Marg (Mansarovar), JLN Marg (Birla Mandir area), Vidhyadhar Nagar, Vaishali Nagar, Jhotwara and Sikar Road · Road

Tonk Road Sinkhole and Citywide Trench Hazards From Gas Pipeline Work

A portion of Tonk Road collapsed into a roughly 20-foot-deep sinkhole in July 2026, one of several similar failures across the city caused by inadequately filled trenches dug for the Torrent Gas pipeline project. Rainfall repeatedly washed away the loose fill material used to close these trenches, exposing dangerous gaps and forcing repeated emergency repairs across multiple neighborhoods.

Blunderlust rating ★ 4.1 · 1,124 reviewsOn record 2026
Never Built
Jawaharlal Nehru (JLN) Marg, from Ambedkar Circle to Jawahar Circle via JDA Circle · Road

JLN Marg Elevated Road Plan Scrapped Over Aesthetics

An elevated road planned along JLN Marg, already included in the state budget, was shelved after Rajasthan Chief Minister Bhajan Lal Sharma raised aesthetic concerns about the corridor's appearance during a review meeting. The JDA has since pivoted to planning an alternative elevated road along Tonk Road instead, which would require removing the existing older flyovers at Gopalpura and Durgapura crossings.

Blunderlust rating ★ 4.6 · 184 reviewsOn record 2025

Spread the word

Share this one.

Download the card for Jaipur Metro and send it to a friend.

Submit a Blunder →
Blunderlust

The civic travel guide to the India we were promised in the brochure. Reviewed without fear, favour, or functioning streetlights.

Destinations

  • Mumbai
  • Bengaluru
  • Ahmedabad
  • All cities

Categories

  • All wonders
  • Flyovers to nowhere
  • Bridges on notice
  • Roads reimagined
  • Skywalks to nowhere
  • Metro in progress
  • Public toilets, theoretically
  • Airports awaiting flights
  • Stations under redevelopment
  • Bus stands nobody uses

The Guide

  • Destinations
  • Submit a blunder
  • The Ledger
  • Photo credits
  • Contact desk

“Bureaucracy is a construction by which a person is conveniently separated from the consequences of his or her actions.”

— Nassim Nicholas Taleb, Skin in the Game
NOTICE — Entries document real, publicly reported infrastructure projects, sourced from news reports and RTI replies (see each entry for citations). Star ratings, reviews and editorial tone are satirical framing; the underlying facts are not, and are omitted for entries involving loss of life. Not affiliated with any government body, political party, or foreign agency.© 2026 Blunderlust · File No. BL/2026/POTHOLE/01
Spread the word

Join the mission.

This is a public list of failed government projects, kept so they stay on record. Pick either one — both take a minute.

1

Share this with at least one person

Just one is enough. Copy the link and send it to friends & family who would find this useful.

2

Know a failed project near you? Tell us

Know a project that failed or never opened? Fill a short form; we just need a news link as proof.

Submit a blunder →
thank you, genuinely!
Blunderlust