On record
The four-laning of the Ludhiana Southern Bypass was tendered in 2010 with a two-year deadline but wasn't completed until 2019 after officials failed to complete inter-department formalities before the tender was allotted; poor PWD-Irrigation Department coordination drove repeated design changes.
The official record states: "Attributed to "apathy" and administrative negligence: inter-departmental formalities were not completed before the tender was allotted."
“Tendered before the formalities were done, finished seven years after they should have been.”— Blunderlust Editorial Desk