Under Repeat Repair

Bowbazar East-West Metro Land Subsidence

Blunderlust rating★★★★★ 4.2 / 5 · 792 reviews⌖ Bowbazar: Durga Pituri Lane and Madan Dutta Lane, central Kolkata, KolkataEntry #03 in Kolkata
Bowbazar East-West Metro Land Subsidence — photo 1

On record

On August 31, 2019, a tunnel-boring machine building the East-West Metro corridor struck an aquifer beneath Bowbazar's soft, historically wetland soil, causing numerous two-century-old buildings on Durga Pituri Lane to crack and partially collapse; 23 houses were demolished. The crisis recurred in May 2022 (3 more houses razed) and October 2022 (10 buildings cracked, 136 more residents evacuated), with a Jadavpur University expert panel subsequently recommending 45 additional houses be razed.

The official record states: "Officials initially blamed the tunnel-boring machine hitting an aquifer; a Jadavpur University expert committee later attributed the area's vulnerability to soft soil over an aquifer on land that was historically wetland, settled since 1709 despite the geological risk."

“The tunnel machine hit an aquifer and two-century-old houses cracked; the compensation was five lakh a home.”— Blunderlust Editorial Desk

Sources

  • https://thefederal.com/states/east/west-bengal/kolkata-metro-why-bowbazar-houses-are-cracking-and-what-the-future-holds
  • https://theprint.in/india/governance/after-kolkata-metro-work-causes-cracks-panel-wants-to-raze-45-british-era-homes-in-bowbazar/1189845/

Visitor reviews Satire

“A tunnel machine hit an aquifer under Durga Pituri Lane and two-hundred-year-old houses cracked open above it.”
ZA Z. Ansari · Kolkata★★★★★
“Twenty-three homes demolished in 2019, three more in 2022, ten cracked that October, and the experts want forty-five more down.”
OB O. Bhatia · Kolkata★★★★★
“Five lakh rupees a house for families whose neighbourhood has been settled since 1709. The metro is very nearly finished.”
WL W. Lobo · Kolkata★★★★★
Blunderlust RecordBL/KOL/2019/MET
Status
Under repeat repair; many families permanently relocated
Category
Metro station
State
West Bengal
Year
First incident August 31, 2019; recurred May and October 2022
Cost to taxpayers
₹14 Cr

Your passport

Unstamped

Stay a moment and this entry goes in your passport.

Kolkata
0 of 10
Nationwide
0
Rank
None yet

1 more for Tourist.

View your passport →

Nearby Attractions

While you're in the area

Full Kolkata guide →
Completed after ~4-year delay
Kalighat Road, approach to Kalighat Temple, Hazra · Skywalk

Kalighat Skywalk: Four-Year Construction Delay

The Kolkata Municipal Corporation began building a "mega" skywalk to Kalighat Temple in 2021, displacing hawkers from the temple approach road and temporarily relocating around 195 traders to makeshift units at Jatin Das Park. Traders were told they would return to permanent stalls within 18 months, but the project dragged on for four years before keys to the new multi-storey market building were finally handed over on March 27, 2025.

Blunderlust rating ★ 4.7 · 200 reviewsOn record 2025
Abandoned
New Market / S.S. Hogg Market, Lindsay Street, central Kolkata · Other

New Market (S.S. Hogg Market) Renovation Stalled

Two years after the West Bengal government allocated ₹26 crore to renovate the 1874-built, Victorian-Gothic New Market (appointing Jadavpur University as consultant for central air-conditioning, seismic retrofitting, and repairs to its drainage, roof and toilets), no actual construction work had started on the deteriorating structure, which has cracked pillars and walls, flooding during rain, and roof leaks, despite housing 3,000 shops that generate ₹25 crore in annual revenue for KMC.

Blunderlust rating ★ 4.7 · 1,227 reviewsOn record 2023
Under Repeat Repair
Joka to Esplanade/Park Street corridor via Taratala, Majerhat, Mominpur and Khidderpore · Metro station

Joka–Esplanade (Purple Line) Metro: Over a Decade of Delay

The Purple Line was sanctioned in 2010-11 to connect Joka with Esplanade, with RVNL awarded the construction contract in 2011. Only the 6.5km Joka-Taratala stretch actually opened, inaugurated by the Prime Minister in December 2022, more than a decade after sanction. The remaining extension toward Park Street/Esplanade remained stuck as of 2026, most recently pending a land-swap deal with Nepal's Consulate General needed to build a ramp between the Mominpur and Khidderpore stations.

Blunderlust rating ★ 4.2 · 520 reviewsOn record 2022

Spread the word

Share this one.

Download the card for Bowbazar East-West Metro Land Subsidence and send it to a friend.

Submit a Blunder →
Blunderlust

The civic travel guide to the India we were promised in the brochure. Reviewed without fear, favour, or functioning streetlights.

Destinations

  • Mumbai
  • Bengaluru
  • Ahmedabad
  • All cities

Categories

  • All wonders
  • Flyovers to nowhere
  • Bridges on notice
  • Roads reimagined
  • Skywalks to nowhere
  • Metro in progress
  • Public toilets, theoretically
  • Airports awaiting flights
  • Stations under redevelopment
  • Bus stands nobody uses

The Guide

  • Destinations
  • Submit a blunder
  • The Ledger
  • Photo credits
  • Contact desk

“Bureaucracy is a construction by which a person is conveniently separated from the consequences of his or her actions.”

— Nassim Nicholas Taleb, Skin in the Game
NOTICE — Entries document real, publicly reported infrastructure projects, sourced from news reports and RTI replies (see each entry for citations). Star ratings, reviews and editorial tone are satirical framing; the underlying facts are not, and are omitted for entries involving loss of life. Not affiliated with any government body, political party, or foreign agency.© 2026 Blunderlust · File No. BL/2026/POTHOLE/01
Spread the word

Join the mission.

This is a public list of failed government projects, kept so they stay on record. Pick either one — both take a minute.

1

Share this with at least one person

Just one is enough. Copy the link and send it to friends & family who would find this useful.

2

Know a failed project near you? Tell us

Know a project that failed or never opened? Fill a short form; we just need a news link as proof.

Submit a blunder →
thank you, genuinely!
Blunderlust