In April 2025, a section of the road surface on the 2012-built Irumbuliyur/Tambaram flyover on GST Road caved in, and a crack was simultaneously found on the flyover's railing wall near its starting point. Just 13 years after construction, the structural deterioration alarmed residents and commuters, prompting police to barricade the area and divert traffic while emergency concrete repairs were carried out.

On record

The official record states: "Tambaram Corporation and Highways officials inspected the spot and began "repair works using concrete," without publicly detailing the root structural cause."

Filed as "Under repeat repair" and dated to Built 2012; incident April 2025, this entry sits under the "₹88 crore (original construction cost)" line of the public accounts.

What to expect

  • Pillars reaching skyward with no deck to justify them.
  • A signboard promising an opening date that has since passed, unbothered.
  • Traffic queuing patiently beneath the unfinished span.
  • Rebar exposed where the road was meant to continue.

Sourcing

1 public source — news reports, RTI replies and civic archives — corroborate this entry. The citation trail is listed below for anyone who would like to follow up with the department concerned.

“A structure that peaked at the render stage.”— Blunderlust Editorial Desk

Sources

  • https://www.dtnext.in/news/chennai/crack-and-cave-in-on-tambaram-flyover-spark-structural-safety-fears-829537

Visitor reviews

“Arrived at closing time and found there was no closing time to speak of. It is 'temporarily' closed, in the municipal sense of temporary.”
TR T. Rao · Chennai★★★★★
“Went on a weekday morning and had the entire place to myself. The only thing on schedule here was the mobilisation advance.”
LM L. Menon · Chennai★★★★★
“Drove past the inauguration hoarding to reach the actual site. It is a masterclass in beginning and nothing else.”
DG D. Ghosh · Chennai★★★★★
Official RecordBL/CHE/2012/FLY
Status
Under repeat repair
Category
Flyover
Locality
Irumbuliyur Junction, GST Road, Mudichur, Tambaram
Year
Built 2012; incident April 2025
Cost to taxpayers
₹88 Cr

How to get there

Located in Irumbuliyur Junction, GST Road, Mudichur, Tambaram, Chennai, Tamil Nadu. Routes and access change often on entries filed as "Under repeat repair" — check current local conditions before visiting.

FlyoverTamil Nadu

Nearby Attractions

While you're in the area

Full Chennai guide →
Koyambedu Flyover Cracks and Corrosion
Under Repeat Repair
Koyambedu Junction / Maduravoyal, along the Chennai bypass corridor · Flyover

Koyambedu Flyover Cracks and Corrosion

The 1.15km Koyambedu flyover, inaugurated by CM M K Stalin, developed multiple potholes, exposed expansion joints and jutting-out steel reinforcement bars within about four years — a hazard flagged by cyclists and commuters.

★ 3.4 · 395 reviewsEst. 2021
Perungalathur Flyover — 23-Year Construction Delay
Under Repeat Repair
Srinivasa Nagar, Old Perungalathur, GST Road towards Tambaram/Vandalur · Flyover

Perungalathur Flyover — 23-Year Construction Delay

First sanctioned in 2001, the flyover stayed incomplete for over two decades because an electricity board substation blocking the alignment was never relocated at the planning stage. Phase 3 only opened in June 2023, leaving roughly 200,000 residents to endure prolonged traffic chaos.

★ 4.2 · 413 reviewsEst. 2001
Nanganallur Under-Construction Flyover Collapse
Collapsed
Near Nanganallur–Thillai Ganga Nagar tunnel, between Velachery and Pallavaram/Parangi Malai · Flyover

Nanganallur Under-Construction Flyover Collapse

A portion of an under-construction flyover in south Chennai collapsed on January 18, 2024. No casualties were reported, but the incident raised fresh questions about construction quality and supervision on active flyover projects.

★ 3.6 · 366 reviewsEst. 2024
Blunderlust

The civic travel guide to the India we were promised in the brochure. Reviewed without fear, favour, or functioning streetlights.

Destinations

  • Mumbai
  • Bengaluru
  • Ahmedabad
  • All cities

Categories

  • All wonders
  • Flyovers to nowhere
  • Bridges on notice
  • Roads reimagined
  • Skywalks to nowhere
  • Metro in progress
  • Public toilets, theoretically

The Guide

  • Destinations
  • Submit a blunder
  • The Ledger
  • Photo credits
  • Contact desk

“Bureaucracy is a construction by which a person is conveniently separated from the consequences of his or her actions.”

— Nassim Nicholas Taleb, Skin in the Game
NOTICE — Entries document real, publicly reported infrastructure projects, sourced from news reports and RTI replies (see each entry for citations). Star ratings, reviews and editorial tone are satirical framing; the underlying facts are not, and are omitted for entries involving loss of life. Not affiliated with any government body.© 2026 Blunderlust · File No. BL/2026/POTHOLE/01