Under Construction

Berhampur Ring Road

Blunderlust rating 3.6 / 5 · 364 reviews⌖ 46km ring road around Berhampur, Chhatrapur, Gopalpur (Ganjam district), BerhampurEntry #01 in Berhampur

On record

Then-CM Naveen Patnaik laid the foundation stone for this ring road in 2013, but land acquisition failures and NHAI non-cooperation meant actual construction of even phase 1 did not begin until November 2021, eight years later.

The official record states: "Officials cited "failure to acquire private land" as the primary cause; the district collector said as of 2023 acquisition had "reached its final stage.""

“Foundation stone in 2013, first construction in 2021. Eight years of a ring road going in circles.”— Blunderlust Editorial Desk

Sources

Visitor reviews Satire

“Foundation stone in 2013, phase one construction in 2021, and the ring is still not a ring.”
TS T. Sundaram · Berhampur
“Eight years were spent not acquiring private land, and the collector says acquisition has reached its final stage, as of 2023.”