Then-CM Naveen Patnaik laid the foundation stone for this ring road in 2013, but land acquisition failures and NHAI non-cooperation meant actual construction of even phase 1 did not begin until November 2021, eight years later.
The official record states: "Officials cited "failure to acquire private land" as the primary cause; the district collector said as of 2023 acquisition had "reached its final stage.""